Drivers in Borehamwood could face delays because of roadworks near the town’s retail park.

Temporary traffic lights are being installed from tomorrow (Monday August 1) in Theobald Street at the junction with Borehamwood Shopping Park.

Planned work by Energetics Electricity is taking place with a permit being granted by Hertfordshire County Council for the work to last until August 11.

Elsewhere, there will be two-way traffic lights from tomorrow until Thursday in Barnet Lane, Elstree.

Affinity Water is carrying out planned work near the junction with The Chantry.

Affinity Water will also be carrying out planned repairs in Shenley Road in Borehamwood a little later in August.

There will be two-way traffic lights close to the junction with Thrift Farm Lane from August 12-16.

Meanwhile, Rowley Lane will be closed in both directions on a stretch between Well End Road and the A1/Holmshill Lane junction on August 4 due to work being carried out by Openreach.

There will also be lane closures in Rowley Lane starting from tomorrow until at least August 13 where the Sky Studios is under construction.